Status of planning activities

The following tables outline the current status of water resource planning activities.

Stage 1—Water resource plans at October 2009

Plan area Preparation announced Draft plan released Final plan approved Amendment activities
Baffle 25 Oct 2006 WRP to include overland flow
Barron N/A 20 Dec 2001 19 Dec 2002 WRP to review provisions for managing unsupplemented and subartesian water in the upper Barron
Border Rivers N/A 8 July 2002 4 Dec 2003 WRP to include supplementary water allocations with NSW-final WRP approved 14 June 2007
Boyne 24 April 1999 23 May 2000 14 Dec 2000  
Burdekin 17 Jan 2002 3 August 2006 2 Aug 2007  
Burnett N/A 26 June 2000 14 Dec 2000 WRP to include groundwater
Calliope 4 Mar 2004 5 August 2006 15 Dec 2006  
Condamine-Balonne N/A 3 Dec 2003 5 Aug 2004 WRP to address groundwater management in Central Condamine Alluvium area.
Cooper Creek N/A 17 Dec 1999 7 Feb 2000  
Fitzroy N/A 3 Sept 1998 23 Dec 1999 Review underway
Georgina-Diamantina 21 Nov 2001 3 Nov 2003 5 Aug 2004  
Gold Coast 1 Oct 2005 10 July 2006 15 Dec 2006
Great Artesian Basin 5 Apr 2005 26 Aug 2005 31 March 2006  
Gulf 6 June 2003 26 Oct 2006 1 Nov 2007  
Logan 21 Nov 2001 6 July 2006 2 March 2007 WRP to include certain water in the Soutern Moreton Bay Islands area
Mary 20 May 2002 18 Nov 2005 28 July 2006  
Mitchell 24 Feb 1999 26 Oct 2006 1 Nov 2007  
Moonie 19 Nov 1998 8 July 2002 4 Dec 2003  
Moreton 21 May 2005 10 July 2006 16 March 2007  
Pioneer N/A 18 Dec 2001 20 Dec 2002 WRP to include groundwater approved 8 October 2009
Warrego/Paroo/Bulloo/Nebine 19 Nov 1998 8 July 2002 4 Dec 2003
Whitsunday 20 March 2006 5 Sep 2008  

Stage 2—Resource operations plans at October 2009

Plan area Preparation announced Draft plan released Final plan approved Amendment activities
Barron 29 Jan 2003 2 Aug 2004 16 Jun 2005  
Border Rivers 8 July 2002 8 Jan 2007 14 Mar 08  
Boyne 24 March 2001 8 Dec 2001 24 July 2003 ROP to include details of water licences through Chapter 7-final ROP approved 20 July 2006
Burdekin 3 Aug 2006 24 Oct 2008    
Burnett 20 Feb 2002 2 Dec 2002 29 May 2003 ROP to include water harvesting and the Barker/Barambah, Boyne catchments and coastal Burnett groundwater management area
Calliope 5 August 2006 29 May 2007 2 May 08  
Condamine and Balonne 3 Dec 2003 27 July 2007 12 Dec 2008  
Cooper Creek A ROP is not required for the Cooper Creek catchment
Fitzroy 23 Nov 2000 2 Dec 2002 9 Jan 2004 ROP to provide for the conversion of water allocations between medium priority and high priority in the Nogoa-Mackenzie Water Supply Scheme approved 9 July 2009.
Georgina-Diamantina 3 Nov 2003 5 Sep 05 13 July 2006  
Gold Coast 10 July 2006 13 Jan 2009
Great Artesian Basin 26 Aug 2005 22 July 2006 23 Feb 2007  
Gulf 3 Nov 2006 24 Oct 2008  
Logan 6 July 2006 17 Dec 2008    
Mary 18 Nov 2005      
Mitchell 3 Nov 2006 24 Oct 2008    
Moonie 8 July 2002 4 Feb 2005 20 January 2006  
Moreton 10 July 2006 13 Jan 2009    
Pioneer 29 Jan 2003 2 Aug 2004 16 Jun 2005 Final ROP amendment approved 28 June 2007 
Warrego/Paroo/Bulloo/Nebine 8 July 2002 4 Feb 2005 20 January 2006
Whitsunday  5 Sep 2008      

Last updated: 30 October 2009