Binary Remediation Project - 13 August
Weekly update
Monday 13 August 2007 to Friday 17 August 2007
To keep local residents, businesses, media and other interested parties fully informed of the remediation of the Narangba Industrial Estate, the department is publishing a weekly update.
The current soil remediation activities are part of the department's ongoing cleanup and remediation works on State and local government-owned land adjacent to the Binary factory site.
A summary of progress and site conditions between Monday 13 August 2007 and Friday 17 August 2007 is provided below:
- The remediation site received 2mm of rainfall this week.
- The department continues to treat contaminated stormwater collected on the site using the specially constructed treatment pond on the project site. Approximately 403 000 litres of treated water was discharged to the Caboolture Shire Council sewer this week.
- Work is due to commence next week, weather permitting, to remove contaminated soil from Pond 1, the last of the four containment ponds to be remediated.
The department has been supervising all works conducted on the site.
Anyone with concerns about odour, soil or water contamination from the Narangba Industrial Estate is advised to contact the department hotline on 1300 130 372.
Media statements
05/03/2008 Building contractor sentenced to jail for environmental harm
18/01/2008 The department investigates wastewater overflow from Caboolture sewerage pipe
Business updates
Media statements
Business updates
Technical information
- Soil, sediment and water testing - dioxins
- The department water sampling program
- post-Binary fire incident
Archives
Last updated: 28 November 2007