Sand placement
Sand Pumping Statistics
Operational Phase (from 4th of May, 2001 to 31st August 2009) |
||
|---|---|---|
|
Cumulative Quantity |
Monthly Report |
Snapper Rocks East |
4,336,326 |
22,853 |
Kirra |
264,112 |
0 |
Snapper Rocks West |
12,264 |
7,797 |
Duranbah |
491,757 |
3,411 |
Greenmount |
31,932 |
0 |
Subtotal |
5,136,391 |
34,061 |
|
|
|
Dredging Placement Statistics |
||
Snapper Rocks East |
730,015 |
0 |
Inner nearshore |
63,920 |
0 |
Centre nearshore |
81,873 |
0 |
Outer nearshore |
277,275 |
0 |
Snapper Rocks West |
149,106 |
0 |
Duranbah |
121,048 |
0 |
Centre nearshore Duranbah |
53,149 |
0 |
Outer nearshore Duranbah |
29,996 |
0 |
Palm Beach |
22,870 |
0 |
Subtotal |
1,529,252 |
0 |
|
|
|
TOTAL |
6,665,643 |
34,061 |
Total volumes of sand moved during the Development phase of the Project
Commissioning tests
| Activity | Dates | Quantity |
|---|---|---|
Optional Dredging Order No. 1 |
1/4/2000 to 5/9/2000 |
324,153 m3 |
Pre-Commissioning dredging and nourishment |
10/11/2000 to 4/5/2001 |
208,365 m3 |
Sub-total by dredge |
532,518 m3 |
|
Pre-Commissioning pumping |
3/3/2001 to 4/5/2001 |
|
Snapper Rocks East |
164,853 m3 |
|
Duranbah |
19,783 m3 |
|
Sub-total by pumping |
184,636 m3 |
|
Total |
x |
717,154 m3 |
30 day trial to Snapper Rocks East |
(March 2001) |
127,466 m3 |
24 hour trial to Snapper Rocks East |
(10/4/2001) |
12,403 m3 |
Last updated: 11 September 2009